Application of Formal Installation of Rectangular Absorption Tower Arranged at High Position
杜国庆 DU Guo-qing
(中国能源建设集团安徽电力建设第二工程有限公司,合肥 230000)
(China Energy Engineering Group Anhui No.2 Electric Power Construction Co.,Ltd.,Hefei 230000,China)
摘要:燃煤电厂烟气脱硫多采用石灰石-石膏湿法脱硫技术,吸收塔为脱硫系统核心设备,随着国家烟气排放标准提高为超净排放,须增强脱硫效率。广州粤电台山发电厂4号机组脱硫吸收塔为日本千代田CT121鼓泡塔技术,脱硫提效改造设计新增一台高位布置矩形吸收塔与鼓泡塔串联,靠新增联络烟道串联,形成双塔循环。本次施工合理选用400t履带吊作为主吊机械,正装法自下而上、由外向内、分层安装吸收塔及塔内装置。
Abstract: The flue gas desulfurization of coal-fired power plants mostly adopts limestone-gypsum wet desulfurization technology. The absorption tower is the core equipment of the desulfurization system. As the national flue gas emission standards are raised to ultra-clean emissions, the desulfurization efficiency must be enhanced. The desulfurization absorption tower of Unit 4 of Guangzhou Yuedian Dianshan Power Plant is Japan's Chiyoda CT121 bubble tower technology. The desulfurization improvement design adds a high-position rectangular absorption tower and the bubble tower in series, and the new connecting flue is connected in series to form Double tower loop. In this construction, a 400t crawler crane was reasonably selected as the main crane, and the absorption tower and the internal device of the tower were installed in layers from bottom to top, from outside to inside.
关键词:高位布置;吸收塔;正装法;自下而上、由外向内分层安装吸收塔及其塔内设备;吸收塔与鼓泡塔串联,双塔循环
Key words: high-level arrangement;absorption tower;straight installation method;layered installation of absorption tower and its internal equipment from bottom to top, from outside to inside;absorption tower and bubbling tower in series, double tower circulation
中图分类号:TM621.8 文献标识码:A 文章编号:1006-4311(2021)31-095-03
DOI:10.3969/j.issn.1006-4311.2021.31.030.
文章出处:杜国庆. 高位布置矩形吸收塔正装施工的应用[J]. 价值工程,2021,40(31):95-97.
|