Study on Stability of Shield Subway Tunnel Closely-underneath-crossing the Existing Tunnel in Round Gravel Soil
孙孝海 SUN Xiao-hai
(中国电建集团昆明勘测设计研究院有限公司,昆明 650000)
(PowerChina Kunming Engineering Corporation Limited,Kunming 650000,China)
摘要:利用大型有限元软件 Midas GTS/NX 建立近距下穿施工的三维模型,探讨既有轨道交通 4 号线和 5 号线在盾构施工中的位移变化。结果表明:①既有隧道各监测点在新建隧道中轴线附近位移变化速率最大;②最佳注浆加固厚度为 0.04m 左右。
Abstract: Midas GTS/NX finite element software is used to establish a three -dimensional model of short -distance underpass construction, and the displacement change of existing rail transit line 4 and Line 5 in shield construction is discussed. The results show that:①The displacement rate of each monitoring point in the existing tunnel is the largest near the central axis of the new tunnel; ②The best grouting reinforcement thickness is about 0.04m.
关键词:近距下穿;盾构隧道;数值模拟
Key words: closely-underneath-crossing;shield tunnel;numerical simulation
中图分类号:U455.43 文献标识码:A 文章编号:1006-4311(2024)28-067-03 doi:10.3969/j.issn.1006-4311.2024.28.020
|